May 6, 2008: The ceilings in the kennel
areas have been painted. The primer coat of paint in the rest of the building has been
completed. Most of the doors have been installed and the framing around the doors has been
started and is well on the way to completion. The ventilation systems are installed. The
lights in the t-bar ceiling have been installed.
 |
 |
 |
| The lighting in the Adoption
Center |
The lighting and painted
ceilings in the main kennel |
The doors going in. |
|
|
|
 |
 |
 |
| The ventilation system in the
quarantine kennel being installed |
The heat recovery system. |
The patio poured in front of
the quarantine kennel |
|
|
|
 |
|
|
| The patio poured in the main
turnout area |
|
|

April 17, 2008: The lighting in the kennel
areas has been put in place. The framework for the drop ceiling is nearly in place. The
outside vents for the kennel areas have been started. The framework for pouring the cement
for the patios has been started.
 |
 |
 |
| The lighting in the
quarantine kennel and the finishing of the walls |
The framework being started
for the patio in the turnout area |
The start of the vents going
in for the kennel areas |
|
|
|
 |
 |
 |
| The lighting in the main
kennel and the finishing of the walls |
The start of the piping for
the sprinkler system |
The framework for the drop
ceiling in the adoption area |
|
|
|
 |
 |
|
| The framework for the drop
ceiling in the training room |
The framework being started
for the patio in the quarantine turnout area |
|

April 8, 2008: The FRP (water-proof
covering) is up on the kennel area walls. The taping and sanding of all the joints in the
wallboard continues.
 |
 |
| The FRP in the main kennel |
Taping and sanding the
ceiling in the kennel |
|
|
 |
 |
| The FRP going up in the
quarantine kennel |
Taping and sanding the main
adoption area |

April 4, 2008: All the drywall/wallboard has been put up.
The support posts for the overhangs continue to be placed. The taping of all the
drywall/wallboard is in progress. The hose reels have been ordered. The application for
the sprinkler permit has been submitted.
 |
 |
 |
| The support posts for the
overhang being put in place. |
The support posts for the
side overhang being put in place. |
The wallboard in place in the
quarantine kennel. |
|
|
|
 |
 |
 |
| The wallboard in place in the
main kennel. |
The taping in progress |
The taping in progress |
|
|
|
 |
 |
|
| The main entry area |
The grass growing in the
landscaping and the plants in place |
|

March 28, 2008: A lot more of the drywall has been
installed. The taping of the seams of the wallboard in the kennel area has been started.
The support beams for the overhangs are being installed.
(Click thumbnails for a better view)
 |
 |
 |
| Wallboard taping in kennel
area |
Support posts being installed |
Support posts being installed |
|
|
|
 |
 |
 |
| Wallboard and taping |
Standing in the warehouse
area looking towards the main entrance |
Standing in the main entrance
looking towards the warehouse area |

March 20, 2008: The wallboard in the kennel areas
continues to go up. The ditches out front have been cleaned up and culverts installed at
strategic locations. A graveled area has been laid out that will be used for extra
parking.
 |
 |
 |
 |
| One of the ditches/culverts |
Another of the ditches |
Another of the
ditches/culverts |
The graveled area |
|
|
|
|
 |
 |
 |
 |
| Wallboard going up in the
main kennel area |
Wallboard in the main kennel
area |
Wallboard in the main kennel
area |
Wallboard in the ceiling over
the kitchen |
|
|
|
|

March 13, 2008: The wallboard is going up in the kennel
area finally. This has been a complex process to ensure the materials used would meet
sound and moisture resistant requirements. The heat is running well in all areas of the
building. There are some kinks still to be worked out on the heating system. The main
building's outside walls have been insulated. They have started digging the holes for the
overhang support poles. The back-up generator has been installed. Decisions have been made
on the ventilation system for the kennel area. Most of the wiring for phones, intercom
system, and electrical have been completed. Most of the plumbing has been completed.
 |
 |
 |
| The wallboard going up on the
kennel area ceiling |
The wallboard going up on the
kennel area ceiling |
Part of the heating system |
|
|
|
 |
 |
 |
| Part of the heating system |
The front entrance insulated
and framed in |
The plumbing for the in-floor
heat in the kennel area |
|
|
|
 |
|
|
| An outside door installed |
|
|

March 4, 2008: The county required landscaping is progressing well. The kennel area roof
has been insulated. The propane tank has been placed, hooked up and filled. The heat in
the kennel area has been tested and started. It is anticipated that they will start
dry-walling the kennel area roof at the end of this week or start of next week once the
kennel area is sufficiently warm and dry.
 |
 |
 |
| The siding pretty well
complete |
The landscaping at the back
of the building |
The landscaping at the side
of the building |
|
|
|
 |
 |
 |
| Another view of the
landscaping at the side of the building |
The propane tank placed |
Another view of the
landscaping at the back of the building. Also, some of the siding. |
|
|
|
 |
|
|
| The front of the kennel
building |
|
|

February 25, 2008: Wiring and plumbing are progressing.
Insulation of the kennel area roof has been started. The siding has basically been
completed. The landscaping is well on its way. Most of the exterior doors have been
placed. The propane tank has been placed.

February 6, 2008: The kitchen/food prep room has been framed in as well as the blanket
storage room. Some more of the siding has been put in place. Also more of the plumbing
piping has been installed and work has been started on the electrical for the kennel
building.
 |
 |
 |
| Some more of the siding in
place |
The blanket storage room
framed in |
The kitchen/prep room framed
in |

January 25, 2008: The kennel floors are poured!!!
 |
 |
| The kennel floors in the main
kennel looking good! |
The kennel floors in the
quarantine kennel also looking good! |

January 22, 2008: The retaining wall on the west side of the building has been put in
place. The insulation and in-floor heating piping has been laid out. The cement pouring
has started in the kennel building. Also, some of the siding has been started on the
buildings. All the exterior windows are in place.
 |
 |
 |
| The ground work for the
retaining wall being completed. |
The retaining wall completed |
The insulation and in-floor
heating piping ready and waiting for the pouring of the cement. |
|
|
|
 |
 |
 |
| The in-floor heating piping
spaghetti |
The first pouring of cement
in the kennel building |
The next pouring of cement in
the kennel building |
December 30, 2007: Some problems solved, insulation
and steel reinforcement installed in kennel floor and floor heat tubing branches out to
keep pups warm.
 |
 |
| This is Moira, Don and Brad
contemplating a minor problem at the year-end on site conference. |
This is Moira, Don and Brad
after the problem solution was found to be simple. |
|
|
 |
 |
| Insulation and steel
reinforcement installed in kennel floor. |
Floor heat tubing branches
out to keep pups warm |
December 16, 2007: An open house was held at the new
kennel so adopters and volunteers could have the opportunity to see the construction
progress.
The new kennel now has an official name: The Hern Greyt
Works. This is in honor of John Hern Jr, our founder. For those of you who knew John he
had a business he ran in Idaho called the Hern Iron Works and the Iron Works housed our
beautiful greyhounds for many years.
Most of the roofing tile has been put in place. The
overhangs are nearly complete on the front and end of the kennel building.
The skylights have been placed both in the main and
quarantine kennel areas.
More of the floor drains in the kennel areas have been
placed.
 |
 |
 |
| Some of the kennel tour
participants. |
More of the kennel tour
participants checking out the new kennel space. |
More of the floor drains in
place in the kennel area. |
|
|
|
 |
 |
 |
| Kennel tour participants
(Mike, Bev, Cathy, Moira & Chris) checking out the turnout area. |
Bob, Mary and Yumi discussing
the new kennel area. |
Kennel building with more of
the roofing tile in place and the skylights inserted. |
|
|
|
 |
 |
|
| The overhang at the end of
the kennel building (in what will be the turnout area). |
the drains being placed in
the quarantine kennel. |
|
December 11, 2007: The roofing is well on
its way. The floor drains in the kennel building are being laid. The front overhang on the
kennel building has been started.
 |
 |
 |
| The floor drains being laid
in the kennel building. |
Moira, Don and the
construction supervisor discussing the merits of skylights. |
The front overhang and
entrance going on the kennel building. |
December 6, 2007: A lot of roof work
is happening on the kennel building. The roof prep work has been nearly completed and the
roofing is going on. Also, some of the drain work is being started in the kennel area.
 |
 |
| The roofing in progress |
The roofing and spaces where
the skylights will be placed in the kennel building. |
|
|
 |
 |
| The back side of the kennel
building |
The drains waiting to be
installed. |
November 28, 2007: The roof trusses have
been set in place and the plywood ready for the roofing has been started. The roof
overhangs are well on their way. Some of the concrete prep has been started in the
existing building.
 |
 |
 |
| The roof trusses being set in
place. |
The plywood for the roofing
in progress |
The roof trusses from inside
the kennel building. |
|
|
|
 |
 |
 |
| The front side of the kennel
building. |
"Build it just like
this...." - Moira talking to Brad the construction supervisor. |
"No, like this...."
- Brad talking to Moira. |
|
|
|
 |
|
|
| The side of the new kennel
building. |
|
|
November 12, 2007: The cul-de-sac and drive
have been leveled and graveled. The trenches for the in-ground heating pipes have been dug
and the pipes have been laid and mostly covered - they are now just waiting for their
final pressure test. The trusses for the roof on the new kennel building have been
delivered.
 |
 |
 |
| The cul-de-sac and drive
being leveled and graveled. |
Rolling the gravel |
Laying the heating pipes |
|
|
|
 |
 |
|
| The heating pipes ready for
the pressure test |
The roof trusses being
delivered |
|
October 29, 2007: The walls of the new
kennel building are up. Also the dog septic system is in progress. So far the tanks for
the dog septic system have been set in place and some of the trenches dug and pipe work
set in place.
 |
 |
 |
| The walls of the new kennel
building are up. |
The tanks for the dog septic
system are in |
The dog septic system going
in. |
October 24, 2007: The foundation and
walls for the kennel building have been poured. Gravel has been poured in for the flooring
of the kennel building. The concrete walls of the kennel building have been insulated. The
entrance to the existing building has been framed out. The overhangs on the existing
building are well on their way. The framing for the walls on the new kennel building has
been started.
 |
 |
 |
| The framing for the entrance
to the existing building in progress. Also the overhangs on the existing building are well
on their way. |
The walls of the kennel
building being insulated. |
Oooh, that's a tight fit. |
|
|
|
 |
 |
 |
| The gravel being poured in
for the floor base of the new kennel building. |
The entrance to the existing
building more complete |
The framing of the doorways
in the kennel building is started |
|
|
|
 |
 |
|
| Framing of the walls |
Framing of the walls |
|
October 12, 2007: The initial drainage
piping has been installed and the concrete poured for the foundation. The water from the
street to the fire hydrant has been turned on so construction can continue.
 |
 |
 |
| Laying some of the drainage
pipe |
Some of the drainage work
completed |
The concrete being poured |
October 1, 2007: The windows for the
existing building have been delivered and partially installed. The framing work for the
foundation for the new building has been started. The food storage room is framed in -
this room will be mouse proofed. The ducting work for the heating/air conditioning in the
existing building is installed. Some of the heating equipment has been set in place.
 |
 |
 |
| The big tree is removed ready
for the next stage of construction. |
The food room is framed in. |
The ducting work in the
existing building. |
|
|
|
 |
 |
|
| The windows are installed in
the existing building. |
The framing work for the
foundation on the new building is started. |
|
|
|
|
September 12, 2007: The tanks for the
septic system have been installed. Also holes in the concrete of the existing building
have been dug so the new plumbing can be installed. The duct work for the heating in the
existing building has been started. The windows for the existing building are on order.
Also, the trenches for the foundation of the new building have been dug.
 |
 |
 |
| Part of the septic system
being installed |
Holes being dug in the
existing building for the new plumbing |
Trenches for the foundation
of the new building being dug |
|
|
|
 |
 |
 |
| The duct work going in |
Greyhounds really can sit.
Frank checking out the new kennel. |
Frank checking out the new
hydrant. |
August 31, 2007: The framing inside the
existing building is well on its way.
 |
 |
| Framing the
inside of the existing building |
August 24, 2007: The water line and hydrant are installed. The framing inside the existing
building is started.
 |
 |
| The water line and fire
hydrant installed |
The start of the framing of
the existing building |
August 16, 2007: To date the prep work has begun in the existing building for putting up
the walls and cutting holes in the concrete for some of the plumbing. Some of the framing
for the windows has begun. All the old shelving in the existing building has been removed.
The property has been cleared where the water line and fire hydrant are to be installed.
Some grading has begun in preparation for the water line. Three of the garage doors we
will not be using from the existing building have been removed and the two insulated ones
have been moved to their new locations in the existing building.
 |
 |
 |
| August 10 - The framing of
the windows in the existing building begins. |
August 10 - The hole is cut
in the building for one of the insulated garage doors. |
August 15 - The clearing of
the land in preparation for the water line installation. |
|
|
|
 |
 |
 |
| August 15 - The silt fences
are installed. |
August 15 - Moira talking to
the water line construction firm |
August 15 - Don talking to
the construction supervisor |
|
|
|
 |
 |
 |
| August 15 - Land clearing in
preparation for the new building. |
August 16 - The site for the
new building is the process of being cleared |
August 16 - Prep work for the
new entrance |
July 30, 2007: Construction Begins!!!
July 8, 2007: Work Party at the new kennel site. We had a work party to clear out the
existing building. A lot of work was done on going through everything, determining what
was to be kept, what was to be thrown out, and what could be given away. Items were then
moved to the storage container, into the little house or put in piles to be trashed or
donated.
July 6, 2007: A storage container was delivered to the site for storing all GPI's
valuables during construction.
June 24, 2007: Groundbreaking Ceremony. The work on the new kennel was kicked off with our
Groundbreaking Ceremony. (Click thumbnails for a
better view)
 |
 |
| The Board |
Group picture at
our groundbreaking event |
|
|
 |
 |
 |
| Our event cake |
Don proposes a toast |
The dogs cut loose |
|